Additions & Renovations Project: District-wide construction management project included 162,000 sf of new roofing
PROJECT DETAILS
Project Title
Additions & Renovations Project
Troy, NY
U.W. MARX SERVICES
Complete pre-construction and construction management services
Project Value
$15.6 million
Construction Completion
2004
DESIGNER
Collins & Scoville Architects (now CSArch)
Albany, NY
PROJECT HIGHLIGHTS
- Multi-phased, District-wide project included improvements at each of the District’s three school buildings
- Project delivered multiple new classrooms, new science labs and gym stations
- New media center constructed at middle school building
- 162,000+ sf of new roofing installed District-wide
- 66,000+ sf of new and renovation construction